Projects and Staffing
Opening a project, moving it through its statuses, staffing it at a rate card, and setting the budget its cost is measured against.
Projects and Staffing
Opening a project
A project manager opens a project from All Projects with New, or from the Projects tab of an account, an opportunity, a contract or an order. A project needs a Project Name and an Account; the Opportunity, Contract and Order it comes from are offered from that account. All three are optional: name the Order when the project delivers a sale that has no contract.
Each project has a Kind:
| Kind | What it is for |
|---|---|
| Presales | Work done to win a deal: a proof of concept, a pilot, a scoping study |
| Delivery | Work the customer bought. Won From points at the presales project it grew out of, if there was one |
| Internal | Work for your own company: practice building, training, tooling |
All three are booked, staffed and costed the same way, so presales effort and internal effort show up as cost just as delivery does. Billing Type (Fixed Fee, Time and Materials, Retainer, Non-billable) records how the customer pays.
Statuses
A project starts as Draft and moves forward one step at a time:
| From | To |
|---|---|
| Draft | In Approval, Cancelled |
| In Approval | Approved, Rejected, back to Draft, Cancelled |
| Approved | Active, Cancelled |
| Rejected | Draft, Cancelled |
| Active | On Hold, Completed, Cancelled |
| On Hold | Active, Cancelled |
| Completed | Closed, or back to Active |
| Closed, Cancelled | Final |
Any other change is refused with a message that lists these steps. A project is never deleted by its manager: a project that will not go ahead is Cancelled, and a finished one is Closed.
Sending a project for approval
A new project starts as Draft. When its plan and budget are ready, the project manager sets Status to In Approval. Its budget's version 1 goes with it, so a project with no version 1, or with one not ready to approve, cannot be sent: the approval is of that budget.
- Every Project Director and PMO holder finds the project in their Inbox (under My Work). The first to decide decides for all.
- A project whose version 1 totals 100,000 or more then goes to the Finance Controllers as well.
- Approved by everyone it went to, the project is Approved, its version 1 becomes the baseline, and the project manager makes it Active when the work starts.
A rejected project is Rejected: move it back to Draft, revise it and send it again. The project manager can also recall it from their Inbox while it waits, which puts it back to Draft.
While it waits, the project is locked and nobody can edit it. Nobody sets Approved or Rejected by hand either: those are written by the approval. Only an administrator can, to repair a project whose approval cannot run.
The budget
Approved Budget is the cost the project may spend. It is not typed: it is the total of the project's baseline budget version, and it changes when a top-up version is approved. Project Budgets explains the versions. Planned Revenue is what the customer pays for the project, and the margin is measured against it.
The project's cost and margin fields fill themselves as hours and expenses are approved. Budget Used % passes 100 % when the project has spent more than its approved budget.
Budget status and the lock
Budget Status follows Budget Used % on its own:
| Budget Status | When |
|---|---|
| On Track | Below 80 % of the Approved Budget |
| Warning | From 80 % |
| Exceeded | From 100 % |
The moment it moves into Warning or Exceeded, the project manager and every Finance Controller get an inbox notice and an email. It comes once per crossing: a project that stays in Warning while more hours are approved sends nothing more.
The notice proposes the lock, and a person decides. Tick Lock Time and Expenses on the project and no timesheet or expense on it can be submitted, whoever submits it. People can still write drafts. Untick it, after agreeing a new budget for example, and submissions are taken again.
A new budget is a top-up version, approved by a Project Director or the PMO, and by finance as well when it raises the Approved Budget by 10 % or more: an approved top-up moves Budget Status at once, so a project is put back On Track only with that approval.
Staffing a project
People are staffed on a project in its Project Members tab, or under Staffing. Each row names:
| Field | What it means |
|---|---|
| Person | Who is staffed. The row is named after them, so lists, search and the confirmation when you create it read their name, and it follows a rename of the user |
| Responsibility | Their part on the project: Project Manager, Project Director, Account Manager, Architect, Consultant, Quality Assurance, Finance Partner or Subcontractor |
| Rate Card | The grade they work at. Their hours are costed and billed at its rates |
| Allocation | The share of their time the project has, as a percentage |
| Start Date, End Date | When they are on the project |
| Billable | Whether their hours are billed to the customer. A non-billable member's hours still cost, but bill nothing |
Staffing someone does two things on the project:
- They can read it. The project's Team lists everyone staffed, the Project Manager included, and each of them reads the project. Remove the row and they lose that access.
- The member whose Responsibility is Project Manager becomes the project's Project Manager. That person reads and edits the project, staffs it and approves its timesheets and expenses. The field is read-only on the project: change it by changing the staffing.
Staff yourself first. A new project has no Project Manager until someone is staffed with that responsibility. The person who opened it can edit it as its owner, but timesheets and expenses created before a manager is staffed have no approver.
Only people staffed on a project can book hours on it.
Rate cards
A Rate Card is a grade of work with two prices:
| Field | What it means |
|---|---|
| Cost Rate | What an hour or a day of this grade costs your company |
| Bill Rate | What the customer is charged for it |
| Unit | Per Hour or Per Day. A day is counted as 8 hours |
| Seniority | Junior, Intermediate, Senior, Lead or Principal |
| Internal | For internal work. Only an internal card may bill less than it costs |
| Effective From, Effective To | When the card is in use, for reference: the card on a member's row is the one that counts |
Finance and the PMO keep the rate cards. Everyone reads them, but the cost rate is hidden from team members.
Changing a rate card never changes past cost. Each time entry copies the rates in force when it is written. Hours booked before a change keep the old rates; hours booked after it get the new ones.