Project Budgets
Planning a project's budget in versions and lines, approving version 1 with the project, raising it with a top-up, and how the Approved Budget follows the baseline.
Project Budgets
A project's budget is planned in Project Budgets: versions, each with its Budget Lines. The approved version in force is the project's baseline, and the project's Approved Budget is its total. Nobody types the Approved Budget: it changes only when a new version is approved.
Versions appear in the project's Related tab, and across every project under Budgets in the Project Delivery app, with the Baselines and Open Versions lists beside All Budget Versions.
Who plans and who decides
| Who | What they can do |
|---|---|
| The project manager, the project's owner, administrators | Make a version, plan its lines and send it for approval |
| Project Directors and the PMO | Approve or reject a version from the Inbox |
| Finance Controllers | Read every version; plan one with the project manager; approve or reject a top-up of 10 % or more |
| People staffed on the project | Nothing: a budget is cost, which is hidden from them, and so is the project's Approved Budget |
A version
| Field | What it means |
|---|---|
| Budget | Its name, filled on save: the project's name and the version, for example Stark Medical Pilot Delivery · v2 |
| Version | Numbered 1, 2, 3… in the order the versions were made |
| Status | Draft, In Approval, Approved, Rejected or Superseded |
| Baseline | Ticked on the one approved version the Approved Budget is taken from |
| Approved With the Project | Ticked on version 1 while it rides on the project's approval |
| Reason | Why the version is needed. Required to send a top-up |
| Total Cost, Labor Cost, Labor Hours | Added up from its lines |
A project has one open version at a time: a new one is refused while another is Draft, In Approval or Rejected. Send it or delete it first. Only an open version can be deleted; an approved or superseded one is the project's history.
A line
| Field | What it means |
|---|---|
| Category | Labor, Subcontracted Services, Third-Party Goods, Expenses or Other |
| Description | What the cost is for |
| Month | The month the cost falls in. Any day typed is saved as the first of its month |
| Rate Card | For a labor line: the level the hours are planned at |
| Hours | For a labor line: the hours planned |
| Quantity | For any other line: how many units |
| Unit Cost | Per hour for labor, per unit otherwise. A labor line with a rate card and no unit cost takes the card's cost rate per hour (a day card's over eight hours) |
| Amount | Hours × unit cost for labor, quantity × unit cost otherwise. It cannot be typed |
A version's lines change only while it is Draft or Rejected. Once it is sent they are locked; plan a change as a new version.
Version 1 goes with the project
A new project's first budget is approved with the project itself:
- The project manager adds version 1 and its lines while the project is Draft.
- Setting the project to In Approval sends version 1 with it. The project is refused if it has no version 1, or if the version is not ready: no lines, a total of zero, a labor line with no rate card or no hours, or another line with no quantity.
- The project's approval decides both. A project whose version 1 totals 100,000 or more also goes to the Finance Controllers.
- Approved: version 1 is Approved and becomes the baseline, and the project's Approved Budget is its total. Rejected or recalled: version 1 goes back to Draft, to be corrected and sent again with the project.
Version 1 cannot be sent on its own while the project has not been approved.
A top-up
When a project needs more, or a different, budget, the project manager makes a new version:
- Add the version from the project's Related tab. It starts as Draft, numbered after the last one.
- Plan its lines as the whole new budget, not only the difference: its total becomes the Approved Budget once it is approved.
- Write the Reason, then set Status to In Approval.
- Any Project Director or PMO holder decides from the Inbox; the first to decide decides for all. A top-up that raises the Approved Budget by 10 % or more then goes to the Finance Controllers as well.
- Approved: the version becomes the baseline, the one before it is Superseded, and the Approved Budget, Budget Remaining, Budget Used % and Budget Status follow at once. Rejected: the baseline stands, and the version can be set back to Draft, corrected and sent again. The project manager can also recall it from the Inbox while it waits.
A project always has at most one baseline.
Projects from before budget versions
A project whose Approved Budget was typed before budget versions keeps that figure. An administrator can carry it over into a version 1, so later top-ups work, with scripts/backfill-project-budget-baseline.ts (see the script's own notes). It only reports until it is run with --apply, and touches no project that already has a version.