The Project Plan
Breaking a project into tasks, drawing them on a Gantt, booking hours against them, and how the project's Percent Complete follows them.
The Project Plan
A project's plan is its Project Tasks. They appear in the project's Related tab, on a Gantt under the project's fields in the Overview tab, and across every project under Project Plan (a Gantt) and Task Tree in the Project Delivery app.
Who writes the plan
| Who | What they can do |
|---|---|
| The project manager, the project's owner, administrators | Add, change and remove tasks. Writing a task needs edit on its project |
| People staffed on the project | Read every task. They cannot change one, so they report progress to the project manager |
| Finance Controllers, Project Directors, the PMO | Read every project's plan |
A task
| Field | What it means |
|---|---|
| Task Name | What the work is |
| Parent Task | The task this one is part of. A task with subtasks is a summary |
| Task Owner | The person who does the task or answers for it |
| Status | Not Started, In Progress, On Hold, Completed or Cancelled |
| Milestone | A checkpoint rather than work, drawn as a diamond |
| Planned Start, Planned End | When the task is planned |
| Predecessors | The tasks that must finish before this one starts |
| Planned Hours | The effort the task is planned at. The project's Percent Complete weighs each task by it |
| Percent Complete | How far along the task is. Set to 100 when the task is Completed |
| Actual Hours | The hours booked against the task |
A Parent Task and every Predecessor must be tasks of the same project. A parent that is one of the task's own subtasks is refused, because the plan would loop.
The Gantt
The Gantt draws the tasks with the predecessors as arrows and milestones as diamonds. Subtasks are listed beside their summary task rather than indented under it: Task Tree in the app shows the tree. Each bar's colour follows the task's status, and its fill follows its Percent Complete.
- Drag a bar to change the task's planned dates, or drag its progress handle to change its Percent Complete. Both save at once.
- Auto-schedule, in the Gantt's toolbar, moves the tasks that wait on a task you moved, and saves them.
Only the Gantt reschedules. There is no server-side cascade: a date changed in the task's form, by an import or over the API moves that task only. Its successors keep their dates until someone moves them.
Hours on a task
A time entry has an optional Task, picked from the timesheet's project; a task of another project is refused. The task's Actual Hours adds up every entry that names it, whatever its timesheet's status. Cost still counts only once the timesheet is approved (see Time and Expenses).
Percent Complete
A project's Percent Complete is worked out from its tasks and cannot be typed. Each time a task changes:
- Take the tasks with no subtasks, leaving out Cancelled ones. A summary task counts through its subtasks, so no hour is counted twice.
- Weigh each one's Percent Complete, 100 for a Completed task, by its Planned Hours.
- Divide by the total planned hours.
| Tasks | Percent Complete |
|---|---|
| Design, 40 h, 50 %; Kick-off, 10 h, Completed | (40 × 50 + 10 × 100) ÷ 50 = 60 % |
| The same, with Design Completed | 100 % |
When none of the counted tasks has planned hours, each counts the same. A project with no task to count shows no percentage.